s_alr_87013558 report logic


Logic

Pass Input Project Code in Table PRPS Field - PSPHI,It will display all WBS of Input Project

get object no - OBJNR against each WBS and Pass to table RPSCO include Field Budget Type = KBFR & value key = 45

and display WBS wise value in Column Budget.

Actual Cost Logic

Pass Input Project Code in Table PRPS Field - PSPHI,It will display all WBS of Input Project.

Step 1- get object no - OBJNR against each WBS.

Step 2- Pass WBS no in table AFVC - PROJN and get Object no OBJNR

Now pass Object no of Step 1 and Step 2 into table COEP field OBJNR,display total of column WKGBTR against each WBS.


Note- Exclude value A for field Offst.acct type (GKOAR) ( If dnt want to consider AUC Transfer Value).

Project Commitment Cost

Pass object no of actual step no 1 in to table COOI Field - OBJNR

& Pass Ref. document catg. REFBT as Preq & Pord

Total Column WKGBTR and display against relevant WBS

Assigned Project Cost

WBS Wise Total of Actual Column Value and Commitment Value

Available

Budget value - Assigned Column value